This project was formulated on the basis to focus on the time required for performing jobs on frame assembly shop of Atlas Honda Pakistan limited (Karachi Plant) by developing a rating factor for each assembly station at the assembly plant and also Reducing of assembly line balance delay by re-balancing of the assembly line. Hence, finally Improving overall productivity through assessment of various human factors at the workplace.				
				
				